MRP#5 - Too Many Action Messages? Why Dampeners Are Essential for Business Central MRP to Avoid Constant Rescheduling

  • Writer: Kevin S. Jones, BC Manufacturing Consultant
    Kevin S. Jones, BC Manufacturing Consultant
  • Mar 27
  • 1 min read

If planners stop trusting MRP, it’s usually because the system produces too much noise.

The Real Issue

Small demand changes trigger:

  • Constant rescheduling

  • Quantity changes of 1 or 2 units

  • Planner fatigue

The Fix: Dampeners

  • Dampener Period → Limits date changes

  • Dampener Quantity → Limits small quantity changes

Best Practice

  • Always use dampeners with Lot‑for‑Lot and Order policies

  • Tune them to suppress noise, not real change

MRP only adds value when planners trust its recommendations.

 
 
 